Question
- Can I see if a student is enrolled in a Free Preview of my course?
Solution
You can view a student user's course enrollment status from the Enrollments tab of their user profile. To access their user profile, click on their name in the User table, under Support Your Students, in the admin dashboard.
To find a list of students enrolled in a Free Preview you can use User Filters (on the Pro + Growth plan or higher):
- Go to Support Your Students
- Select Users
- Select Filters
- Filter for Enrolled in > Free Preview > Course Name
Another way to check if a student is enrolled in a Free Preview is using the Progress Reports feature. If a student is enrolled in a Free Preview, their Activated at date will be empty in the progress report.
Learn More About
What's the difference between a Free Preview and Free Trial subscription period?